Server Re-Location -Timeline for Option 1 Physical MoveHome : Latest News : Time Line for Option 1 - Physical Move : Overview
| Saturday 02/08/08 | |
| 02/08/2008 15:00 | Servers will start to be shutdown gracefully |
| 02/08/2008 17:00 | Shutdown of all servers complete |
| 02/08/2008 17:00 | Servers to be de-racked, wrapped in bubble-wrap and packed into rubberised crates |
| 02/08/2008 20:00 | Crates to be relocated via specialist IT Relocation Company to The Dataport |
| Sunday 03/08/08 | |
| 03/08/2008 06:30 | Crates arrive at The Dataport |
| 03/08/2008 07:00 | Servers to be removed from crates and re-racked |
| 03/08/2008 10:00 | All servers should be re-racked and booted. Move complete. |
|