Server Re-Location -Timeline for Option 1 Physical Move

Home : Latest News : Time Line for Option 1 - Physical Move : Overview

Saturday 02/08/08  
02/08/2008 15:00 Servers will start to be shutdown gracefully
02/08/2008 17:00 Shutdown of all servers complete
02/08/2008 17:00 Servers to be de-racked, wrapped in bubble-wrap and packed into rubberised crates
02/08/2008 20:00 Crates to be relocated via specialist IT Relocation Company to The Dataport
   
Sunday 03/08/08  
03/08/2008 06:30 Crates arrive at The Dataport
03/08/2008 07:00 Servers to be removed from crates and re-racked
03/08/2008 10:00 All servers should be re-racked and booted. Move complete.
   
 

Issue Date: 28/07/2008